This is one of the most challenging projects we have worked on. So many complexities at the site. Importantly it’s a fast-track project. The client wants these units in 5 Weeks at the site when the standard manufacturing time takes more than 6-8 weeks. The units were put in priority production completed on time and Air freighted. More than 4500 Kgs.
It’s in Souq Area and constructed building, there were more challenges to take the units to its respective location.
The project involves DX Type Closed controls units – 4 # units. With units working as working and Standby with Auto change over.
More challenging was commissioning with all site activities going parallel we had a challenging task ahead of us to complete on time.